NorthWest Energy is replacing three power poles along their line from Butte to Ramsey on a small isolated Forest Service parcel at Nissler Junction near the intersection of Interstates 15 and 90.
Location
Not in a Landscape or Management Area. This isolated parcel is the hill next to the interchange for Interstates 15 and 90 on the southwest side.
Project timeline
1
Scoping Start
05/17/2016
2
Decision
07/2016 (Estimated)
3
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Nissler Junction Power Pole Replacement | Decision Signed Date: 07/15/2016 |
| Forests | Beaverhead-Deerlodge National Forest |
| Districts | Butte Ranger District |
| Legal Land Description | Half on T3N, R9W, Section 13 the other half on T3N, R8W, Section |