We propose to install up to three hardened stream crossings and sections of fence at primary livestock crossing sites on the lower reach of Selway Creek. The project would protect streambanks, reduce sediment, and narrow the stream channel.
Location
Lima Tendoy Landscape, Selway Saginaw Management Area
Project timeline
1
Scoping Start
04/19/2017
2
Decision
02/2019 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements; Watershed Improvements |
| Selway Meadows Hardened Stream Crossings | Decision Signed Date: 02/15/2019 |
| Forests | Beaverhead-Deerlodge National Forest |
| Districts | Dillon Ranger District |
| Legal Land Description | T8S, R15W, Sections 14 & 23 |