This project involves replacement and upgrade of an existing overhead electric distribution system with a buried distribution system.
Location
Georgetown Lake Management Area, Clark Fork Flint Landscape
Project timeline
1
Scoping Start
06/06/2017
2
Decision
07/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| NorthWestern Energy Georgetown Lake Underground Powerline Installation | Decision Signed Date: 07/22/2017 |
| Forests | Beaverhead-Deerlodge National Forest |
| Districts | Pintler Ranger District |