Decision Memo Completed

Cliff Creek Bridge Replacement

Idaho Panhandle National Forests Shoshone, Idaho St. Maries Ranger District

Replace and widen the Cliff Creek Bridge on Road 326 and realign the approach.

Location

Map #10 - Road 326 at Cliff Creek on the St. Joe Ranger District in the Loop Creek Drainage

Project timeline

1
Scoping Start
11/19/2009
2
Decision
03/2010 (Estimated)
3
Implementation
09/2010 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Cliff Creek Bridge Replacement and Remedial Bridge RepairsDecision Signed Date: 03/26/2010
ForestsIdaho Panhandle National Forest
DistrictsAvery Ranger District
Legal Land DescriptionSection 10, T46N, R6E, Boise Meridian