Replace and widen the Cliff Creek Bridge on Road 326 and realign the approach.
Location
Map #10 - Road 326 at Cliff Creek on the St. Joe Ranger District in the Loop Creek Drainage
Project timeline
1
Scoping Start
11/19/2009
2
Decision
03/2010 (Estimated)
3
Implementation
09/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Cliff Creek Bridge Replacement and Remedial Bridge Repairs | Decision Signed Date: 03/26/2010 |
| Forests | Idaho Panhandle National Forest |
| Districts | Avery Ranger District |
| Legal Land Description | Section 10, T46N, R6E, Boise Meridian |