Decision Memo Completed

Green Slate

Idaho Panhandle National Forests Shoshone, Idaho Avery Ranger District

70 acres of commercial thin with 1/4 mile of temporary road construction

Location

Map #1 - St. Joe Ranger District - Slate Creek Drainage between Mack Gulch and Horn Gulch

Project timeline

1
Scoping Start
02/09/2011
2
Comment Period
02/14/2011
3
Decision
03/2012 (Estimated)
4
Implementation
05/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements; Timber Sales (Green)
Green SlateDecision Signed Date: 12/05/2011 (FS Withdrawn) Legal Notice Date: 12/09/2011
Green Slate II Decision MemoDecision Signed Date: 03/16/2012 Legal Notice Date: 03/17/2012
ForestsIdaho Panhandle National Forest
DistrictsAvery Ranger District
Legal Land DescriptionSection 24, T46N, R4E, Boise Meridian