Reduce the risk of sediment entering the drinking water through road improvements, road decommissioning, vegetation and fuels management, and to improve grizzly bear habitat.
Location
Twenty Mile Creek and Brown Creek drainages.
Project timeline
1
Scoping Start
03/02/2012
2
Comment Period
04/05/2013
3
Objection Period Start
04/18/2014
4
Decision
09/2016 (Estimated)
5
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green); Watershed Improvements |
| Twentymile Creek | Decision Signed Date: 06/13/2014 |
| Black Mountain Lookout Tower Relocation | Decision Signed Date: 09/13/2016 |
| Forests | Idaho Panhandle National Forest |
| Districts | Bonners Ferry Ranger District |
| Legal Land Description | T61N, R1E, Sections 25, 26, 35, 36. T61N, R2E, Sections 30, 31. T60N, R1E, Sections 1, 2, 12. T60N, R2E, Sections 6, 7, 18. BM |