The Quartz Beetle project is 19 miles East of Avery in the Quartz Creek drainage of the St Joe River. The Project will consist of commercial thinning on approzimately 65 acres.
Location
Project #5 - 19 miles east of Avery in the Quarz Creek area
Project timeline
1
Scoping Start
10/26/2012
2
Comment Period
10/26/2012
3
Decision
04/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Green) |
| Quartz Beetle Decision Memo | Decision Signed Date: 04/23/2013 Legal Notice Date: 04/29/2013 |
| Forests | Idaho Panhandle National Forest |
| Districts | Avery Ranger District |
| Legal Land Description | T45N, R8E, Sec: 14, 15, B.M. |