Ecosystem restoration in various forest types. Project purposes include reducing sediment to Boulder Creek and protecting emergency communication equipment on Black Mountain from wildfire.
Location
The Boulder Creek project is located on federally managed lands in the Boulder Creek Watershed and includes the drainages east of Katka peak.
Project timeline
1
Scoping Start
12/09/2016
2
Comment Period
10/06/2017
3
Objection Period Start
07/24/2018
4
Decision
10/2018 (Estimated)
5
Implementation
11/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green); Watershed Improvements |
| Boulder Creek Restoration Project | Decision Signed Date: 10/29/2018 |
| Boulder Creek Restoration Project, Decision Notice | Decision Signed Date: 10/29/2018 |
| Forests | Idaho Panhandle National Forest |
| Districts | Bonners Ferry Ranger District |
| Legal Land Description | Federal lands in all or portions of: T61N, R2E, Sections 1-2, 11-13, 20-36. T61N, R3E, Sections 5-9, 16-22, 27-34. T60N, R2E, Sect. 1-36. T60N, R3E, Sect. 3-9, 16-20, 29-30. T59N, R2E, Sect. 4,BM |