Installation of a backup generator, load transfer switch, and four 25-gallon liquid propane fuel storage tanks for use in the event of a power outage.
Location
Lakeview Mountain Communication Site
Project timeline
1
Scoping Start
05/22/2014
2
Decision
10/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Priest Lake Translator District Backup Generator Project | Decision Signed Date: 10/22/2014 |
| Forests | Idaho Panhandle National Forest |
| Districts | Priest Lake Ranger District |
| Legal Land Description | T61N, R4W, SE1/4 SW1/4 Section 31, B.M. |