Decision Memo Completed

Priest Lake Translator District Backup Generator and Fuel Storage

Idaho Panhandle National Forests Bonner, Idaho Priest Lake Ranger District

Installation of a backup generator, load transfer switch, and four 25-gallon liquid propane fuel storage tanks for use in the event of a power outage.

Location

Lakeview Mountain Communication Site

Project timeline

1
Scoping Start
05/22/2014
2
Decision
10/2014 (Estimated)
3
Implementation
10/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Priest Lake Translator District Backup Generator ProjectDecision Signed Date: 10/22/2014
ForestsIdaho Panhandle National Forest
DistrictsPriest Lake Ranger District
Legal Land DescriptionT61N, R4W, SE1/4 SW1/4 Section 31, B.M.
Special use management