Approximately 6500 acres would be treated in previously harvested areas that were then planted and naturally regenerated with trees.
Location
St Joe Ranger District
Project timeline
1
Scoping Start
03/03/2015
2
Decision
07/2015 (Estimated)
3
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| St Joe Timber Stand Improvement Project: 2015 | Decision Signed Date: 07/01/2015 |
| Forests | Idaho Panhandle National Forest |
| Districts | St. Maries Ranger District |
| Legal Land Description | Not Applicable |