Protect the health and safety of the public by removing hazardous trees, capture the economic value of the dead and dying timber, and reforest areas burned by the Tower Fire.
Location
Upper West Branch Priest River Drainage including Paqua Creek, Klhowya Creek, Galena Creek, Solo Creek, and North Fork Goose Creek.
Project timeline
1
Scoping Start
01/29/2016
2
Comment Period
01/29/2016
3
Decision
06/2016 (Estimated)
4
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Tower Fire Salvage and Reforestation Project | Decision Signed Date: 06/23/2016 |
| Forests | Idaho Panhandle National Forest |
| Districts | Priest Lake Ranger District |
| Legal Land Description | T35N-R45E, T35N-R44E, T34N-R45E, and T34N-R44E, WM |