Convey an isolated parcel of NFS lands to the City of Spirit Lake, comprising 158.74 acres, through the authority of the Townsite Act. The land conveyance would enable the City to acquire land adjacent to its current wastewater treatment site.
Location
Two miles north of the City of Sprit Lake, north of State Highway 41 and west of the Spirit Lake Cutoff Road.
Project timeline
1
Scoping Start
11/24/2021
2
Comment Period
11/24/2021
3
Objection Period Start
05/09/2022
4
Decision
08/2022 (Estimated)
5
Implementation
08/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Purchases |
| City of Spirit Lake Townsite Act Conveyance | Decision Signed Date: 08/01/2022 |
| Forests | Idaho Panhandle National Forest |
| Districts | Sandpoint Ranger District |
| Legal Land Description | SE of section 30, T. 54 N., R. 4 W, Boise Meridian |