Replacement of nine aging greenhouses and adjoining structures at the Coeur d'Alene Nursery to improve safety and efficiency, helping to meet increasing demands for seedlings for reforestation.
Location
3600 W. Nursery Road, Coeur d%u2019Alene, Idaho
Project timeline
1
Scoping Start
04/25/2022
2
Decision
06/2022 (Estimated)
3
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Coeur d'Alene Nursery Capital Investment Project | Decision Signed Date: 06/13/2022 |
| Forests | Idaho Panhandle National Forest |
| Districts | Idaho Panhandle National Forest All Units |
| Legal Land Description | Not Applicable |