Project timeline

1
Scoping Start
03/26/2007
2
Comment Period
03/26/2007
3
Decision
01/2011 (Estimated)
4
Implementation
07/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning
ForestsLolo National Forest
DistrictsNinemile Ranger District; Plains/Thompson Falls Ranger District; Superior Ranger District
Legal Land DescriptionPrimary the Ninemile and Trout Creek Drainages
Road managementWatershed managementWildlife, fish, rare plants