The Lolo Post Burn EIS decision was not upheld in court. This project would issue a new decision to complete restoration activities originally analyzed in the EIS.Timber harvest is not proposed, only road stabilization, storage, and decommissioning
Location
Ninemile, Superior, and Plains Ranger Districts on the Lolo National Forest
Project timeline
1
Scoping Start
03/26/2007
2
Comment Period
03/26/2007
3
Decision
01/2011 (Estimated)
4
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning |
| Forests | Lolo National Forest |
| Districts | Ninemile Ranger District; Plains/Thompson Falls Ranger District; Superior Ranger District |
| Legal Land Description | Primary the Ninemile and Trout Creek Drainages |