Vegetative treatments to improve forest health and reduce fuels
Location
Seeley Lake Ranger District
Project timeline
1
Scoping Start
07/11/2008
2
Comment Period
07/11/2008
3
Decision
07/2009 (Estimated)
4
Implementation
06/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Auggie Creek restoration/Fuels Project | Decision Signed Date: 07/27/2009 Legal Notice Date: 07/29/2009 |
| Forests | Lolo National Forest |
| Districts | Seeley Lake Ranger District |
| Legal Land Description | T17N, R15W, Sec. 24, 25, 26, 27, 34 & 35 - T17N, R14W, Sec. 32 |