Trail construction and reconstruction to connect existing trail segments, creating a 100-mile long non-motorized trail across the Lolo, Bitterroot, and Beaverhead National Forests on the Sapphire Divide.
Location
Sapphire Divide
Project timeline
1
Scoping Start
04/16/2010
2
Decision
08/2011 (Estimated)
3
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Lolo National Forest |
| Districts | Missoula Ranger District |
| Legal Land Description | T12N, R19W, Sections 12,13; T12N, R18W, Sections 18, 19, 20,21,27,28 and 24; T11N, R18W, Sections 3,10,15,22,27,26 and 36 and T10N, R18 W, Section 2 |