Integrated landscape management including forest vegetation restoration, wildlife habitat and watershed improvements, and recreation enhancements within the Clear Creek drainage.
Location
Clear Creek drainage within the Prospect watershed about 3 miles west of Thompson Falls, Montana
Project timeline
1
Scoping Start
04/06/2010
2
Comment Period
09/07/2012
3
Objection Period Start
12/06/2013
4
Decision
09/2014 (Estimated)
5
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Species Habitat Improvements; Trail Management; Noxious Weed Treatments; Road Maintenance; Timber Sales (Green); Watershed Improvements |
| Clear Creek Project | Decision Signed Date: 09/02/2014 |
| Forests | Lolo National Forest |
| Districts | Lolo National Forest All Units |
| Legal Land Description | T21N, R30-32W; T22N, R30-32W |