Application by Missoula Electric Cooperative to bury 2.25 miles of existing overhead power lines and replace one utility pole on National Forest System Lands near U.S. Highway 12 in the Lolo Creek Drainage.
Location
15 miles west of Lolo, Montana on North side of U.S. Highway 12, between Clark Creek and a location 2 miles east of MDT maintenance facility near Martin Creek.
Project timeline
1
Scoping Start
08/26/2010
2
Comment Period
03/2011 (Estimated)
3
Decision
04/2011 (Estimated)
4
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Forests | Lolo National Forest |
| Districts | Missoula Ranger District |
| Legal Land Description | Section 29, T12N, R22W, and Sections 24, 25, 26, and 34, T12N, R23W |