This project would re-route the groomed snowmobile trail to avoid two stream crossings that have undersized culverts. Trail would be mostly clearing a route that a 9-foot groomer can travel through; but will not have tread for summer use.
Location
Snowmobile trail 63
Project timeline
1
Scoping Start
03/06/2014
2
Decision
04/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Watershed Improvements |
| Drew Creek Snowmobile Trail Re-route | Decision Signed Date: 04/10/2014 |
| Forests | Lolo National Forest |
| Districts | Seeley Lake Ranger District |
| Legal Land Description | Township 16 North, Range 14 West, Section 18 |