Proposed treatments to accomplish the project objectives include tree thinning and slashing, prescribed fire, weed treatments, and road treatments.
Location
South of I-90 and Alberton and Huson, MT in Sawmill, Reservoir, Petty, Peppard, Tank, and Corral Creek drainages.
Project timeline
1
Scoping Start
10/10/2019
2
Comment Period
09/04/2020
3
Objection Period Start
12/29/2020
4
Decision
03/2023 (Estimated)
5
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Roadless Area Management; Road Maintenance; Road Improvements/Construction; Travel Management; Timber Sales (Green); Watershed Improvements |
| Sawmill-Petty Project Final Decision Notice | Decision Signed Date: 03/28/2023 |
| Sawmill-Petty Project | Decision Signed Date: 03/28/2023 |
| Forests | Lolo National Forest |
| Districts | Ninemile Ranger District |
| Legal Land Description | SE 1/4 , NE 1/4, S 34, T14N, R 23W, MT Meridian |