Project includes vegetation, road, and recreation management activities to restore resilient vegetative conditions, reduce fuels, enhance recreation opportunities, and support communities. It also contains a proposal to amend the Forest Plan.
Location
The project area of approximately 44,000 acres is between St. Regis and Superior in the Mill, Fourmile, Slowey, Keystone, and Pardee Creek drainages, and on the north slope facing into Highway 135.
Project timeline
1
Scoping Start
12/15/2021
2
Comment Period
08/09/2023
3
04/26/2024
4
Decision
04/2024 (Estimated)
5
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | 2021 Infrastructure: Emergency Actions |
| Notice and Comment Regulation | 2021 Infrastructure: Emergency Actions |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Travel Management; Timber Sales (Green) |
| Superior North | Decision Signed Date: 04/26/2024 |
| Forests | Lolo National Forest |
| Districts | Superior Ranger District |
| Legal Land Description | Not Applicable |