Winter Park Ski Area Master Plan Phase 1 project proposals. Chairlift upgrades, general area improvements, snowmaking modifications, snow fence installation, and vegetation management.
Location
Winter Park Ski Resort
Project timeline
1
Scoping Start
02/25/2005
2
Comment Period
11/2005 (Estimated)
3
Decision
04/2006 (Estimated)
4
Implementation
05/2006 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Forest Vegetation Improvements |
| Winter Park Resort Phase I Projects Decision Notice and FONSI | Decision Signed Date: 04/28/2006 Legal Notice Date: 05/02/2006 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Sulphur Ranger District |