Forest Supervisor Glenn P. Casamassa has signed a decision memo allowing Noble Energy Inc. (Noble) to construct approx. 2,100 feet (0.40 mile) of buried, 6-inch steel natural gas pipeline on the Pawnee National Grassland.
Location
The pipeline would be located approximately a mile southwest of Keota,Colorado
Project timeline
1
Scoping Start
06/10/2013
2
Comment Period
06/10/2013
3
Decision
08/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| DECISION MEMO AMEND AN EXISTING SPECIAL USE PERMIT for NOBLE ENERGY, INC | Decision Signed Date: 08/13/2013 Legal Notice Date: 08/22/2013 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Pawnee Ranger District |
| Legal Land Description | T.8N.,R.60W.6th P.M., sec.4 N1/2SE1/4 |