The Forest Service proposes to authorize the replacement of approximately 4,400 feet of the Ranch Creek Canal with buried pipe.
Location
The project is located along NFSR 128 on the east side of US Hwy. 40 across from Winter Park Resort and adjacent to the Lakota development. The canal will be replaced between Cub Creek and Buck Creek.
Project timeline
1
Scoping Start
10/23/2019
2
Decision
12/2019 (Estimated)
3
Implementation
07/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Denver Water Ranch Creek Canal Replacement Project | Decision Signed Date: 12/18/2019 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Sulphur Ranger District |
| Legal Land Description | Not Applicable |