Allow replacement of a Parshall Flume located within the existing Bob Creek Ditch at the headwaters of Roaring Creek. Existing flume is failing and must be replaced in order for Greeley to be credited for the water they divert.
Location
T9N, R75W, Sec 11
Project timeline
1
Scoping Start
09/15/2019
2
Decision
02/2020 (Estimated)
3
Implementation
03/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Decision Memo - CLRD SUA City of Greeley Parshall Flume replacement | Decision Signed Date: 02/24/2020 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Canyon Lakes Ranger District |
| Legal Land Description | Not Applicable |