Environmental Assessment Completed

2021 East Pawnee Power Line Project

Arapaho and Roosevelt National Forests & Pawnee National Grassland Weld, Colorado Pawnee Ranger District

The U.S. Forest Service proposes to authorize construction, operation, and maintenance of 1 mile of overhead power line (115 kV) on the Pawnee National Grassland.

Location

The Project Area is about 17.5 miles east-northeast of Grover, Colorado.

Project timeline

1
Scoping Start
02/03/2021
2
Comment Period
02/05/2021
3
Objection Period Start
05/26/2021
4
Decision
09/2021 (Estimated)
5
Implementation
09/2021 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
2021 East Pawnee Power Line Project DN & FONSIDecision Signed Date: 09/02/2021
ForestsArapaho and Roosevelt National Forests
DistrictsPawnee Ranger District
Legal Land DescriptionT. 11 N., R. 58 W., 6th P.M., section 18, E1/2E1/2.
Special use management