Decision Memo Completed

Lombard 3 Plan Of Operation

Arapaho and Roosevelt National Forests & Pawnee National Grassland Clear Creek, Colorado Clear Creek Ranger District

The Forest Service proposes to authorize a mining plan of operation. The plan includes use of mechanized equipment to open a closed adit, sample and evaluate material, stockpile material and secure adit.

Location

East of Alice in the Alice Yankee Hill Mining District

Project timeline

1
Scoping Start
02/11/2021
2
Decision
08/2021 (Estimated)
3
Implementation
08/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Lombard 3 Plan Of OperationDecision Signed Date: 08/12/2021
ForestsArapaho and Roosevelt National Forests
DistrictsClear Creek Ranger District
Legal Land DescriptionT.3S, R.34W, Sec. 1, 6th PM
Minerals and geology