Remove and replace electric transmission lines burned in the 2020 East Troublesome Fire and install underground vaults along three miles of Highway 125 and two miles along National Forest System Road 101.8.
Location
Junction of Hwy 125 and NFSR 108.1
Project timeline
1
Scoping Start
01/05/2021
2
Decision
06/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| MPEI Hwy 125/NFSR 108.1 Install New Underground Electric and Rebuild Overhead Electric Service | Decision Signed Date: 06/24/2021 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Sulphur Ranger District |
| Legal Land Description | Sec. 1, 2, 3, 12 T4N R78W; Sec. 7, 18, 29 T4N R77W |