PSCo proposes to replace 1 distribution pole and install 2 new distribution poles located along Van Eden Road on NFS
Location
Van Eden Road
Project timeline
1
Scoping Start
02/09/2023
2
Decision
07/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| PSCo Van Eden Line Distribution Line Extension | Decision Signed Date: 07/21/2023 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Clear Creek Ranger District |
| Legal Land Description | Not Applicable |