Decision Memo Completed

PSCo Van Eden Line Distribution Line Extension

Arapaho and Roosevelt National Forests & Pawnee National Grassland Clear Creek, Colorado Clear Creek Ranger District

PSCo proposes to replace 1 distribution pole and install 2 new distribution poles located along Van Eden Road on NFS

Location

Van Eden Road

Project timeline

1
Scoping Start
02/09/2023
2
Decision
07/2023 (Estimated)
3
Implementation
08/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
PSCo Van Eden Line Distribution Line ExtensionDecision Signed Date: 07/21/2023
ForestsArapaho and Roosevelt National Forests
DistrictsClear Creek Ranger District
Legal Land DescriptionNot Applicable
Special use management