Northern Water proposes to use a combination of process-based restoration techniques and structures and conventional road work in order to improve water quality and floodplain connectivity following the 2020 East Troublesome Fire on Stillwater Creek.
Location
The proposed project is located on Sulphur Ranger District on National Forest System Road (NFSR) 123, Stillwater Pass Road, at Stillwater Creek.
Project timeline
1
Scoping Start
02/09/2023
2
Decision
06/2024 (Estimated)
3
Implementation
07/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Stillwater Creek Road and Channel Resiliency Project | Decision Signed Date: 06/14/2024 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Sulphur Ranger District |
| Legal Land Description | Not Applicable |