Project timeline

1
Scoping Start
02/09/2023
2
Decision
06/2024 (Estimated)
3
Implementation
07/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Willow Creek AvulsionDecision Signed Date: 06/14/2024
ForestsArapaho and Roosevelt National Forests
DistrictsSulphur Ranger District
Legal Land DescriptionNot Applicable
Watershed management