The Pawnee Ranger District proposes to remove the Wildhorse Dam to improve safety and restore the natural stream channel and flood plain.
Location
The project area is located on the Pawnee Ranger District.
Project timeline
1
Scoping Start
08/10/2023
2
Comment Period
02/05/2024
3
Decision
09/2024 (Estimated)
4
Implementation
10/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Wildhorse Dam Decommissioning and Removal Project | Decision Signed Date: 09/24/2024 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Pawnee Ranger District |
| Legal Land Description | Township - 9N, Range -60W, Sec - 26 |