Realign portions of the Roaring Creek trail to sustainable locations, then rehabilitate damaged and unsustainable trail corridors.
Location
2.5-4.8 miles of the Roaring Creek Trail heading North from the Roaring Creek Trailhead on State Highway 14
Project timeline
1
Scoping Start
10/13/2023
2
Decision
06/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Upper Roaring Creek Trail Realignment | Decision Signed Date: 06/24/2024 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Canyon Lakes Ranger District |
| Legal Land Description | Township 9N, Range 75W, Section 14 |