Jefferson County wants to replace the culvert along Brook Forest Rd at Maxwell Falls Lower TH due to material loss and significant corrosion with widespread corrosion holes and failed joints throughout the pipe.
Location
Maxwell Falls and Cub Creek; T. 5 S., R. 71 W. Sec 29, 31; T 6 S., R 71 W. Sec 6
Project timeline
1
Scoping Start
04/11/2024
2
Decision
10/2024 (Estimated)
3
Implementation
10/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Jefferson County FRTA Easement and Brook Forest Rd/Maxwell Falls Lower Trailhead Culvert Replacement | Decision Signed Date: 10/21/2024 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Clear Creek Ranger District |
| Legal Land Description | Not Applicable |