Decision Memo Completed

AT&T Standby Generator Installation Project at Loveland Ski Area

Arapaho and Roosevelt National Forests & Pawnee National Grassland Clear Creek, Colorado Clear Creek Ranger District

The AT&T Initiative for Cellular Network Reliability requires that an emergency backup generator be installed at the Loveland Ski Area Communication Site to ensure cellular and First Net First Responder Network emergency coverage.

Location

Loveland Ski Area, at T4S, R76W, Sec. 28

Project timeline

1
Scoping Start
09/06/2024
2
Decision
12/2024 (Estimated)
3
Implementation
06/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
AT&T Standby Generator Installation Project at Loveland Ski AreaDecision Signed Date: 12/16/2024
ForestsArapaho and Roosevelt National Forests
DistrictsClear Creek Ranger District
Legal Land DescriptionNot Applicable
Special use management