This purpose of this project is to replace the current Howitzer systems for triggering avalanches with remote avalanche systems, in order to eliminate the need for ammunition whose availability is declining and increase public and employee safety.
Location
Mount Bethel, at T4S, R76W, Sec. 14 and 15
Project timeline
1
Scoping Start
09/06/2024
2
Decision
01/2025 (Estimated)
3
Implementation
01/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Mt Bethel Avalanche RACS | Decision Signed Date: 01/16/2025 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Clear Creek Ranger District |
| Legal Land Description | Not Applicable |