Mitigate wetlands lost during railroad construction.This includes shallow excavations at 3 sites along Antelope Creek to create wetland habitat. Includes temporary work sites, and uses existing roads. A total of 16 acres would be excavated.
Location
Antelope Creek
Project timeline
1
Scoping Start
03/07/2008
2
Comment Period
03/07/2008
3
Objection Period Start
12/2013 (Estimated)
4
Decision
02/2014 (Estimated)
5
Implementation
03/2014 (Estimated)
NEPA / regulatory detail
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | T40N, R69W, Sections 5, 8, 9, and 15; T40N, R68W, Section 20 |