New fiber optic line would be placed in the right-of-way of Wyoming highway 450, 90, and 387. This would be on 4.13 miles of National Grassland.
Location
Highways 450, 59, and 387.
Project timeline
1
Scoping Start
03/27/2009
2
Comment Period
03/28/2009
3
Decision
12/2011 (Estimated)
4
Implementation
01/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| RT Communications, Inc Keeline to Wright Fiber Optic Upgrade | Decision Signed Date: 12/16/2011 Legal Notice Date: 12/22/2011 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | T43N, R69W; T43N, R70W; T43N, R71W |