Rehabilitation of approximately 1 mile of an old ditch on Forest Service land that has several large breaches and gullies. Located in roadless.
Location
Rabbit Ears Pass - Dumont Lake Area-Long Park Roadless Area
Project timeline
1
Scoping Start
12/21/2009
2
Comment Period
01/31/2010
3
Decision
08/2011 (Estimated)
4
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Four Counties Ditch Rehabilitation Project | Decision Signed Date: 08/22/2011 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Hahns Peak/Bears Ears Ranger District |
| Legal Land Description | T5N, R82W, Sec. 7 & 8 |