Antelope Coal LLC has requested an authorization to amend the existing Antelope Mine special use permit to allow expansion of the railroad spur area associated with expansion and increased capacity of the coal loadout facility.
Location
Hilight Bill Geographic Area
Project timeline
1
Scoping Start
12/15/2010
2
Comment Period
06/19/2013
3
Decision
09/2013 (Estimated)
4
Implementation
11/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Cloud Peak Energy, LLC Antelope Mine Plant Expansion-Railroad Spur | Decision Signed Date: 09/25/2013 Legal Notice Date: 09/27/2013 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | W 1/2, SW 1/4, Section 1; W 1/2, Section 12; W 1/2, Section 13; SE 1/4, SE 1/4, Section 14, T 40 N, R 71 W, Converse County, Wyoming. |