Decision Memo Completed

PreCorp SUP for Ballard Wildhorse Federal #14--18

Medicine Bow-Routt National Forests & Thunder Basin National Grassland Campbell, Wyoming Douglas and Thunder Basin Ranger District

This project would allow the installation of <2 miles of <33kV line to the Wildhorse Federal well 14-18. The proposed route would utilize the existing road corridor.

Location

York Road in the Spring Creek Area of the Thunder Basin National Grassland

Project timeline

1
Scoping Start
05/01/2011
2
Decision
12/2011 (Estimated)
3
Implementation
01/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityForest Service Energy Implementation Plan
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Minerals Or Geology Plans Of Operations
PRECorp Electrical Line to Ballard Wildhorse Creek Federal WellsDecision Signed Date: 12/14/2011
ForestsMedicine Bow-Routt National Forest
DistrictsDouglas and Thunder Basin Ranger District
Legal Land DescriptionT 54 N, R 70 W, Sections 13 and 24
Minerals and geology