This project would allow the installation of <2 miles of <33kV line to the Wildhorse Federal well 14-18. The proposed route would utilize the existing road corridor.
Location
York Road in the Spring Creek Area of the Thunder Basin National Grassland
Project timeline
1
Scoping Start
05/01/2011
2
Decision
12/2011 (Estimated)
3
Implementation
01/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| PRECorp Electrical Line to Ballard Wildhorse Creek Federal Wells | Decision Signed Date: 12/14/2011 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | T 54 N, R 70 W, Sections 13 and 24 |