Environmental Assessment Completed

NFSRs 807/879 Reconstruction

Medicine Bow-Routt National Forests & Thunder Basin National Grassland Carbon, Wyoming Brush Creek/Hayden Ranger District

Reconstruct a 4.0 mile segment of NFSR 807 between the Battle Creek CG and NFSR 851. Reconstruct a 1.0 mile segment of NFSR 879 between the NFSR 807 junction and NFSR 879.1E. Reconstruction is needed to fix roadway design and drainage deficiencies.

Location

Roughly 20 miles southwest of Encampment, Wyoming, south of the Battle Highway (Hwy 70)

Project timeline

1
Scoping Start
10/05/2010
2
Comment Period
10/05/2010
3
Decision
04/2012 (Estimated)
4
Implementation
08/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Maintenance; Road Improvements/Construction
NFSR 807/879 ReconstructionDecision Signed Date: 04/16/2012 Legal Notice Date: 04/17/2012
ForestsMedicine Bow-Routt National Forest
DistrictsBrush Creek/Hayden Ranger District
Road management