Decision Memo Completed

DCP Douglas, LLC Natural Gas Pipeline to EOG Well

Medicine Bow-Routt National Forests & Thunder Basin National Grassland Converse, Wyoming Douglas and Thunder Basin Ranger District

DCP will construct two 4inch natural gas pipelines; one high pressure steel line, one low pressure poly pipe, to the EOG-Arbalest 53-33H well to tie into their existing 4inch high pressure line. Less than 5 acres of NFS lands.

Location

Approximately 6 miles north of the Jenny Trail Hwy 59 Junction then approximately 3 miles east of Hwy 59.

Project timeline

1
Scoping Start
12/09/2011
2
Decision
01/2012 (Estimated)
3
Implementation
02/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityOil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390)
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
DCP Douglas, LLC Proposed Natural Gas Pipeline To EOG Arbalest 53-33H WellDecision Signed Date: 01/17/2012
ForestsMedicine Bow-Routt National Forest
DistrictsDouglas and Thunder Basin Ranger District
Legal Land DescriptionT41N, R72W, Sec 34 NW1/4NW1/4
Minerals and geology