Decision Memo Completed

Lester Creek (Pearl Lake) Dam Repair

Medicine Bow-Routt National Forests & Thunder Basin National Grassland Routt, Colorado Hahns Peak/Bears Ears Ranger District

CO Dept of Parks & Wildlife proposal for the installation of 200 LF of toe drain pipe, 45 tons of riprap bedding and 130 tons of riprap, to increase the stability of the right abutment and dewater the left abutment.

Location

Pearl Lake, Lester Creek Dam

Project timeline

1
Scoping Start
04/21/2012
2
Comment Period
04/21/2012
3
Decision
07/2012 (Estimated)
4
Implementation
08/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Lester Creek (Pearl Lake) Dam RepairDecision Signed Date: 07/25/2012 Legal Notice Date: 07/29/2012
ForestsMedicine Bow-Routt National Forest
DistrictsHahns Peak/Bears Ears Ranger District
Legal Land DescriptionSection 35, SW1/4 T10N, R85W
Special use management