The Forest Service proposes to issue new leases and extend existing leases for several permittees at the Hill 8821 and Crow Creek Hill communication sites.
Location
Pole Mountain communication sites at Hill 8821 and Crow Creek Hill
Project timeline
1
Scoping Start
05/19/2014
2
Decision
07/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Communication Site Permits at Hill 8821 and Crow Creek Hill | Decision Signed Date: 06/25/2014 |
| SourceGas LLC, Versatel, Western Area Power Association | Decision Signed Date: 07/11/2014 |
| Southern Star, Hill 8821 | Decision Signed Date: 07/25/2014 |
| Mauna Towers, LLC: Crow Creek | Decision Signed Date: 07/29/2014 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Laramie Ranger District |
| Legal Land Description | Not Applicable |