Environmental Assessment Cancelled

Wyoming Pipeline Company-Butte Junction Crude Oil Pipeline Replacement

Medicine Bow-Routt National Forests & Thunder Basin National Grassland Weston, Wyoming Douglas and Thunder Basin Ranger District

The USFS is proposing to authorize Wyoming Pipeline Co to replace 3.2 miles of is existing crude oil pipeline. The work would require an additional 10 ft outside of the existing 20 ft ROW to complete construction activities.

Location

From the Butte Junction station to the soutwest side of Beaver Creek, west of Newcastle, WY

Project timeline

1
Scoping Start
08/20/2014
2
Comment Period
08/20/2014
3
Objection Period Start
06/2015 (Estimated)
4
Decision
07/2015 (Estimated)
5
Implementation
07/2015 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
ForestsMedicine Bow-Routt National Forest
DistrictsDouglas and Thunder Basin Ranger District
Legal Land DescriptionT44N, R63W Sec11, SE1/4 to T44N, R63W Sec 5 NE1/4
Special use management