The USFS is proposing to authorize Wyoming Pipeline Co to replace 3.2 miles of is existing crude oil pipeline. The work would require an additional 10 ft outside of the existing 20 ft ROW to complete construction activities.
Location
From the Butte Junction station to the soutwest side of Beaver Creek, west of Newcastle, WY
Project timeline
1
Scoping Start
08/20/2014
2
Comment Period
08/20/2014
3
Objection Period Start
06/2015 (Estimated)
4
Decision
07/2015 (Estimated)
5
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | T44N, R63W Sec11, SE1/4 to T44N, R63W Sec 5 NE1/4 |