Authorization for an existing 1,970-foot 14.4kV distribution electrical overhead power line that provides service to several oil wells. The authorization would be for operation and maintenance of the power line and right-of-way.
Location
Thunder Basin National Grassland; approx. 16.5 miles west of Bill, WY.
Project timeline
1
Scoping Start
01/30/2015
2
Decision
04/2016 (Estimated)
3
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | W2SE sec. 34 T38N R73W, 6th P.M. |