This project will remove two weirs and associated infrastructure from Coon Creek and the Upper East Fork Encampment River. The access road will be decommissioned, and a culvert will be removed from Forest road 416.1C to allow aquatic organism passage
Location
T12N, R83W, Sections 7 and 8, within the Encampment River addition Inventoried Roadless Area.
Project timeline
1
Scoping Start
08/04/2014
2
Decision
02/2015 (Estimated)
3
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Coon Creek and Upper East Fork Encampment River Weir Removal | Decision Signed Date: 02/27/2015 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Brush Creek/Hayden Ranger District |
| Legal Land Description | Not Applicable |