Replace existing culvert with a larger culvert or a bridge to address engineering structural and safety concerns and improve aquatic passage and hydrologic conditions.
Location
Approximately 1.25 miles south of Gould, Colorado
Project timeline
1
Scoping Start
04/01/2015
2
Decision
01/2017 (Estimated)
3
Implementation
06/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Watershed Improvements |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Parks Ranger District |
| Legal Land Description | T6N, R77W, Sec 10 |