Construction of new overhead 69kV powerline (5-wire; single, treated wood poles), originating from PRECorp Tekla substation and crossing 4,935 feet Federal lands, providing service for DCP Midstream to a natural gas pump station off federal land.
Location
Project is corridored along Matheson Road and Basin Electric 230 Kv powerline in Campbell County, WY.
Project timeline
1
Scoping Start
07/2015 (Estimated)
2
Comment Period
08/2015 (Estimated)
3
Objection Period Start
11/2015 (Estimated)
4
Decision
01/2016 (Estimated)
5
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | SNE, NWNE, NNW of Sec 3, T41N R71W |